Screeding Contractors: Getting Floor Levels Right Before the Finish Goes Down

Smooth grey flowing screed across a new-build apartment floor

Set your floor datum early. Choose the screed for the build-up and the programme. Then verify the surface and moisture before the finish goes down.

A floor can look level and still cause problems later. Variations in height, the wrong screed specification or moisture trapped beneath a finish can all affect the next trade. Getting these decisions right at the start helps protect your programme and gives flooring contractors a sound, well-prepared base to work from.

For developers and main contractors, the key is coordination. Your screed type, thickness, floor finish, underfloor heating and acoustic requirements need to work together. Here’s what to consider when planning screeding on a commercial or residential project.

Choose the screed to suit the build-up

There’s no single screed that suits every floor. Your choice depends on the substrate, required thickness, intended finish, site access, programme and any heating or acoustic components.

Traditional sand-cement screed

A traditional sand-cement screed can be used in bonded, unbonded or floating constructions, depending on the design. It’s a familiar, adaptable option, but the specification and installation need to suit the substrate and required performance.

Consider it where the design calls for a conventional cement-based screed and the programme allows for curing and drying. Agree the mix, thickness, joints and finish expectations in advance. Site conditions and workmanship matter: inconsistent mixing, poor compaction or unsuitable curing can affect the finished surface.

Flowing screed, including anhydrite

Flowing screeds are delivered and placed in a fluid state, which can make them useful across larger floor areas or where pipes and services need to be surrounded. Calcium-sulphate, often called anhydrite, is one type. It is commonly considered for underfloor heating because it can flow around heating pipes.

Don’t assume that a flowing screed is ready for floor finishes as soon as it can be walked on. Some calcium-sulphate screeds also need surface laitance removed and the correct preparation before a compatible primer, smoothing compound, tile adhesive or other floor system is applied. Confirm the required preparation with the screed and flooring manufacturers.

Fast-drying or rapid-hardening screed

Where programme pressure is high, a proprietary fast-drying or rapid-hardening screed may be an option. But check exactly what the product’s stated times mean. A surface that is walkable or ready for light traffic is not necessarily ready for vinyl, timber, resin or another moisture-sensitive finish.

Ask for the product name, permitted thickness, installation conditions, drying guidance and required moisture test. Don’t substitute a general drying rule for the manufacturer’s instructions.

Operatives levelling a traditional screed on a construction site

Plan drying and moisture testing into the programme

Allow time for screed to dry before the flooring trade is booked. As a broad planning guide, conventional sand-cement screed is often estimated at around one day per millimetre up to 50 mm in favourable drying conditions. That is only an estimate. Greater thickness, cool temperatures, high humidity, poor ventilation and moisture from other works can extend the drying period.

A 50 mm screed can take around two months to dry under favourable conditions. Actual timing depends on the screed and site, so treat estimates as a planning aid, not a handover test. Fast-drying products have their own requirements, and anhydrite screeds may dry at a different rate.

Before the floor finish is installed, check moisture using a method suitable for the screed and in line with the flooring system requirements. A surface meter can help identify areas for further investigation, but it should not automatically be treated as final acceptance evidence. Many moisture-sensitive flooring systems use a maximum of 75% relative humidity as a benchmark, but the limits set by the relevant screed, adhesive and flooring manufacturers take precedence.

Record the test locations, method, readings and conditions. That gives you a clearer basis for coordinating the next trade and agreeing whether the floor is ready. For further guidance, see Floorscape’s overview of moisture testing in concrete floors and screeds and the Gyvlon post-installation guidance.

Agree levels and surface regularity before installation

Set the finished floor datum before the screed is laid. Check how the proposed build-up relates to door thresholds, stair nosings, lifts, adjacent rooms, drainage falls and the thickness of the final floor finish. If these details are left until later, you may be trying to solve a level issue after the screed is already in place.

Specify the required surface regularity as well. Under BS 8204, surface regularity is commonly assessed using a 2 m straightedge. The familiar SR classes allow maximum gaps of 3 mm for SR1, 5 mm for SR2 and 10 mm for SR3. The right class depends on the project specification and the intended finish; a demanding thin finish may need a different level of preparation than a more forgiving covering.

A straightedge check measures local deviation over 2 m. It does not, by itself, confirm the overall floor level or whether the floor suits a particular finish. Agree the acceptance class, test locations and any remedial process before the work starts. The Concrete Society’s guidance on surface regularity explains the straightedge method.

Coordinate underfloor heating before the pour

If your floor includes underfloor heating, bring the screeding and heating teams into the conversation early. Confirm pipe layout, cover, screed thickness, joints, heating zones and commissioning responsibilities against the relevant design and product guidance.

Protect pipes before the screed is placed and make sure the heating installation has been checked as required. Once the screed has cured for the period specified by the system, follow the manufacturer’s commissioning procedure, including any staged temperature changes. Record the process. Then carry out the required moisture checks before flooring preparation begins.

Underfloor heating pipes laid out across an unfinished apartment floor

Treat acoustic floor build-ups as a complete system

In flats, the floor may include a structural slab, a resilient acoustic layer, a separating membrane, a floating screed and a floor finish. The exact build-up needs to meet the project’s acoustic, structural, fire, services and finished-level requirements. It should be designed and coordinated, not improvised on site.

Pay attention to the edges and penetrations. A floating floor can lose its intended isolation if screed or finishing materials create a rigid bridge to the walls, or if service penetrations and perimeter details are not handled as specified. Keep perimeter isolation continuous and check that the selected screed is compatible with the resilient layer and its load requirements.

Coordinate the details with your acoustic designer and the relevant system suppliers. The NHBC guidance on underfloor heating also covers considerations for screed and heating build-ups.

Illustration of an acoustic floating-floor build-up in cross-section

Avoid common site mistakes

A little coordination now can prevent avoidable delays later. Watch for:

  • Unclear finished levels: confirm datums and interfaces with adjoining trades before installation.
  • A poorly prepared base: check the substrate, membranes and insulation against the agreed specification.
  • Rushed drying: don’t approve a floor finish by appearance, elapsed time or foot traffic alone.
  • Missed preparation: confirm whether the screed needs abrasion, cleaning, priming or a compatible smoothing layer.
  • Unplanned joints or penetrations: coordinate these with the screed, heating and acoustic designs.
  • Unprotected work: control access and protect the floor from damage while other trades continue.

Bring the flooring sequence together

Your screed is one part of a connected internal package. It needs to align with the substrate, heating, acoustic design, floor finish and the wider sequence of works. That is why choosing experienced screeding contractors and agreeing responsibilities early matters.

P&P Palomo Properties Ltd. supports projects from tender stage through to contract completion, working in partnership with clients and helping specify products to meet design needs and budget. Our teams cover screeding alongside plastering, drylining and other internal trades across London, Kent, Essex and the Midlands. Explore our services and company information.

Set the specification, levels, test method and handover responsibilities before installation. Then communicate changes as the programme evolves. You’ll give the flooring contractor a clearer starting point, and your project a better chance of keeping its finish on track.